Northview Heights Estates

Project: Northview Heights Estates - Family - Modifications required to create certified UFAS Units

Project Description: Complete a variety of modifications to dwelling units, common areas, service providers spaces, and the site to meet the criteria of the Uniform Federal Accessibility Standards (UFAS) for this location.

This work includes conversion of townhouse style side by side units to apartment style stacked flats units, in order to create 26 flat units meeting UFAS requirements and 26 non-UFAS units, for a total of 52 units.

Name of Contractor Work Completed Revised Budget Amount Amount Expended Total Jobs (FTEs)
John Zottola Landscaping, Inc. Site Work Construction $1,662,933.23 $1,662,933.23 4.72
Franjo Construction Corp. General Construction $4,603,730.17 $4,603,730.17 24.96
JKECO Electrical Construction $976,063.92 $976,063.92 3.96
Wheels Mechanical Contracting & Supplier, Inc. Plumbing Construction $1,771,506.21 $1,771,506.21 3.39
  Subtotal Unit & Non-dwelling construction $8,283,001.65 $8,283,001.65  
Renaissance 3 Architects Construction Administration & Added Design $343,726.37 $343,726.37 1.21
Turner Construction Company Construction Management Services $834,023.36 $834,023.36 3.20
Total   $11,123,684.61 $11,123,684.61 45.34